The expressway itself is finished. It has been open end to end since August 2025. But much of what will shape life along it over the next few years is still being built, waiting for approvals, or stuck. Brochures tend to list all of it as "coming soon". Here is where each project actually stands as of November 2026, with the date of the latest report we could find.
At a glance
| Project | Where it stands | Latest report |
|---|---|---|
| Global City (HSIIDC) | Phase 1 infrastructure about 80% done, rest due by December | Oct 2026 |
| Gurugram Metro Phase 1 (with Sector 101 spur) | About 15% built, due 2028 | Oct 2026 |
| Gurugram Metro Phase 2 | ₹1,662 crore civil tender cleared | Oct 2026 |
| Underground interchange for Global City | Announced, ₹923 crore, awaiting clearances | Apr 2026 |
| Dwarka Expressway–Vasant Kunj tunnel link | Cabinet approved, ₹6,969.67 crore | Jul 2026 |
| Kherki Daula toll plaza shift | Moving about 13 km to Kukdola | Sep 2026 |
| Bijwasan railway station | Tree-felling cleared, 2 to 8 platforms | Jun 2026 |
| Yashobhoomi Phase 2 | Planned on PPP, no award reported | 2025 |
| Diplomatic Enclave II, Dwarka | Stuck over land acquisition | 2020 |
Global City, Gurugram
The biggest project next to the corridor: a 1,000-acre "city within a city" being developed by HSIIDC between Sectors 36A, 37B and 99A. In October 2026 The Tribune reported that the first-phase infrastructure contract, about ₹940 crore covering roughly 570 acres, is about 80% complete, with the rest expected by December. HSIIDC is auctioning plots, and several large developers have shown interest. The Haryana government expects investment of about ₹1 lakh crore over time.
What hasn't happened yet: we found no published 2026 auction results, and the plan for India's tallest tower is still at proposal stage. In February the state's industries minister said no bidder had been finalised. We have a full page on Global City, with a map and the new projects next to it.

Gurugram Metro
Phase 1 runs about 15 km from Millennium City Centre to Sector 9, with a spur to Sector 101 near Dwarka Expressway. Work started in September 2025. By October 2026 it was reported to be about 15% complete, with completion targeted for 2028. Some stretches still have to clear encroachments and utility lines. In August, Metro Rail News reported a November 2026 deadline to clear the right of way on the Hero Honda Chowk section. We found no separate progress report for the Sector 101 spur.
Phase 2 (Sector 9 to DLF Cyber City) moved forward in October when Haryana cleared a ₹1,662 crore civil-works tender after World Bank approval in June.
What it means for buyers: the metro is real and under way, but Sector 101 won't have a working station for some years. Price it in as a 2028-plus benefit, not a present one.
A new interchange for Global City
In March 2026 an NHAI official said work on a ₹923 crore, four-lane underground trumpet interchange near the Pataudi Road junction would start within three months. It is fully funded by HSIIDC and expected to take about 30 months to build. In April, HSIIDC was still seeking GMDA approval, with land, utility and environmental clearances needed before tendering. We haven't found a report confirming that construction has started.
Dwarka Expressway to Vasant Kunj
In July 2026 the Union Cabinet approved a ₹6,969.67 crore, 8.1 km six-lane link from the Shiv Murti end of the expressway to Nelson Mandela Marg in Vasant Kunj. It includes a 3.14 km twin-tube tunnel, most of it under the Ridge. No completion date has been announced, but when it's done it will give the Delhi end of the corridor a direct route into South Delhi. That's one more reason the Delhi-end sectors are in demand.
Tolls and the Kherki Daula plaza
Tolling at Bijwasan on the Delhi section started in November 2025, at ₹220 one way for cars. Local residents can buy a monthly pass. The Kherki Daula toll plaza on NH-48 is being moved about 13 km to Kukdola near Pachgaon, with barrier-less (MLFF) lanes. Reports differ on whether it will have 12 or 14 lanes. Check the latest toll rates before you plan a daily commute.
Bijwasan railway station
The redevelopment of Bijwasan station, right next to the Delhi end of the expressway, cleared a key hurdle in May 2026 when tree felling and transplanting was allowed in Dwarka Sector 21. The plan takes it from 2 platforms to 8. No completion date has been published.
Yashobhoomi Phase 2
Yashobhoomi, the India International Convention and Expo Centre in Dwarka Sector 25, opened its first phase in 2023. The second phase adds exhibition halls, plus an arena, hotels, retail and offices through public-private partnership. Bidding was said to "begin soon" in March 2025, but we found no report of an award since then.
Diplomatic Enclave II
Often mentioned in brochures, rarely in the news. The Cabinet approved the land transfer for a second diplomatic enclave in Dwarka Sector 24 in 2017. In 2020 the Ministry of External Affairs told Parliament it was stuck over a pending land-acquisition case. We haven't found any newer official update. Treat it as uncertain.
How to use this when you buy
- Pay for what exists, hope for what's coming. The expressway, Yashobhoomi Phase 1 and the airport are here now. The metro, the tunnel and Global City are years away.
- Check the latest date, not the brochure. Where the last news is from 2020, as with Diplomatic Enclave II, don't count on it.
- Look at where each project lands. The Delhi-end sectors (106–113) gain most from the tunnel and Bijwasan. Sectors 99–103 and 36A–37D sit closest to Global City and the metro spur. Browse them on our sector pages.
We'll update this page as new reports come in.
Sources
- The Tribune: Govt woos Gujarat industry with Global City project in Gurugram (Oct 2026)
- ThePrint: The long road to Gurugram's 'city within a city' (Aug 2026)
- Swarajya: Plans for India's tallest building at Global City (Feb 2026)
- Swarajya: Haryana approves ₹1,662 crore Gurugram Metro Phase 2 tender (Oct 2026)
- Metro Rail News: Gurugram Metro utility shifting (Aug 2026)
- Swarajya: ₹923 crore underground interchange on Dwarka Expressway (Mar 2026)
- Construction World: HSIIDC seeks GMDA nod for underpass (Apr 2026)
- DD India: Cabinet approves tunnel link to Vasant Kunj (Jul 2026)
- The Tribune: Tolling begins on Dwarka Expressway (Nov 2025)
- Construction World: Kherki Daula toll plaza shift (Jul 2026)
- Swarajya: Bijwasan rail terminal approval (Jun 2026)
- IICC (Yashobhoomi): About us
- Business Standard: Dwarka diplomatic enclave project stuck (Jan 2020)
- #DwarkaExpressway
- #GlobalCity
- #GurugramMetro
- #Infrastructure
- #UpcomingProjects